Introducing Our First UK Case Study: Enhancing Production Line Reliability at IPSEN Biopharm

We’re excited to share our first UK case study, highlighting how SMS EU partnered with IPSEN Biopharm Ltd to restore and strengthen production line reliability at their Wrexham facility. Through a comprehensive asset assessment and a full Reliability Centered Maintenance (RCM) program, we delivered an optimized 52-week PPM schedule, enhanced asset insights, and measurable reductions in unplanned downtime.

This focused 16-week initiative has improved operational efficiency across the site and continues to guide ongoing maintenance improvements.